I celebrated Ada Lovelace day by working on a difficult logic
problem. If someone is on a holiday’s included shift pattern for part of the
year and then moves off internally to a holidays excluded pattern, how much holiday
do they have left to take?
It may sound easy but the logic was quite daunting. The
shift pattern accounted for their hours and basic holiday. Then they could take
additional holiday while on shift if they were entitled to more than their
basic. Plus they could swap shifts and training was in addition. Oh and they
also did overtime too. So all in all a very typical shift operation designed
for ideal circumstances and then continually adapted to fit the changing environment.
So pro rata estimates were invalid because the shift pattern
did not remain continuous for the whole year. Hence I had to take the recorded
hours they had worked, then the holiday they had taken into account plus the
hours they were due to be scheduled on when they moved off the shift pattern.
So a lot of maths later I had a logically sound answer.
So how much holiday would you give a person who is on a 37.5
hour week, and is due to be moved off the rota on 1st December? He
is entitled to 30 days of holiday plus Bank Holidays. The rota accounted for
only 30 days during the year. He has worked 1580 hours (or scheduled to work
including sickness) up until 1st December. Then he moves onto an
office shift pattern. He has also had 37.5 hours of training and taken 24 hours
of holiday in addition to the holidays included shift pattern.
So what’s the answer?
Well first we need to
know how many hours he will be scheduled to work on an office shift pattern. There
are four weeks and three days in December. So that would be 172.5 hours.
Then we work out how
many hours he should have been scheduled for during the year. 1,955.25 hours.
He has worked 1,641.5
up until 1st December.
So the holiday that
was included in the rota was 1,955.25-1,641.5-172.5=141.25 hours
So he was entitled to
285 hours of holiday during the year. He has taken 24 hours and been scheduled
for 141.25 hours of holiday. Therefore logically he is entitled to 119.75 hours
of holiday in December. There are two Bank Holidays in December so that takes
care of 15 hours of holiday (two days of 7.5-hours). But that still leaves
104.75 hours or 11 days.
That is half of December!
So your options are,
- Force him to take holiday before moving to the new post
- Schedule him to be off on some shifts before December
- Pay overtime
- Carry over holiday
- Buy back the holiday
You may be asking how
the answer could be so high. Well it’s a holiday included shift pattern. So while
over the year he would have worked the correct number of hours, you have to
allow for him being rostered off for more time during part of the year. So because
he is being removed mid cycle his hours do not represent an average amount.
So swapping people on
and off a holidays included shift pattern mid cycle could leave you with high
overtime bills!
If you need help
working out staffing costs or shift pattern drop us an email at alec@visualrota.co.uk or call on +44
(0) 1636 816466